  "title": "Nepal legal baseline & comparison matrix",
  "edition": "Kathmandu Valley permit-authority verification · 3 November 2026",
  "checked_on": "2026-11-03",
  "scope": "Selected directive and water-law provisions have been examined, including the Valley Board’s 2082 regulations. KVWSMB’s groundwater permit role is text-supported; later changes, site boundaries and project conditions still require confirmation.",
  "sources": [
    {
      "id": "NP01",
      "title": "Data Center and Cloud Service (Operation and Management) Directives, 2081 — ministry publication",
      "url": "https://mocit.gov.np/content/13003/data-center-and-cloud-service--operations-and/",
      "kind": "Nepal government publication",
      "status": "Official publication metadata reviewed",
      "checked_on": "2026-11-03",
      "pinpoint": "Ministry publication page; Nepali text examined separately at NP11",
      "summary": "The ministry identifies the 2081 directive. Its webpage date is publication metadata, not proof of commencement or the latest consolidated version.",
      "verification_needed": "Compare the publication attachment with NP11; check later amendments and implementation instruments. Do not substitute webpage upload dates for legal commencement."
    },
    {
      "id": "NP02",
      "title": "Data-center directive — government-hosted unofficial English translation",
      "url": "https://giwmscdntwo.gov.np/media/pdf_upload/data%20center%20translation_bhnhhri.pdf",
      "kind": "Government-hosted translation",
      "status": "Indexed excerpt only",
      "checked_on": "2026-11-03",
      "pinpoint": "Preamble and clauses 1–2, indexed excerpt",
      "summary": "The indexed unofficial translation invokes Electronic Transactions Act section 79 and commencement on approval. Its reported January 28, 2025 approval date is not independently confirmed here.",
      "verification_needed": "Full English PDF retrieval timed out. Signed Nepali scan NP11 appears to show 2081/10/15; reconcile the calendar conversion and any later instruments before calculating a transition deadline."
    },
    {
      "id": "NP03",
      "title": "Foreign Investment and Technology Transfer Act, 2019 (2075)",
      "url": "https://dmgnepal.gov.np/uploads/documents/the-foreign-investment-and-technology-transfer-act-2019-2075pdf-9958-911-1688107036.pdf",
      "kind": "Government-hosted English legal text",
      "status": "Text reviewed; currency pending",
      "checked_on": "2026-11-03",
      "pinpoint": "Sections 1(2), 3–4, 7 and 15; PDF pp. 1, 3–4, 6",
      "summary": "The reviewed English text permits foreign investment subject to exclusions and approval requirements. It addresses technology-transfer agreements and investment applications; sections 10–11 have notification-dependent commencement.",
      "verification_needed": "Check current amended Nepali Act, gazette notifications, rules, sector classification, thresholds and approving body. Do not treat this older English PDF as a current consolidated statement."
    },
    {
      "id": "NP04",
      "title": "Water Resources Act, 2049 (1992) — English text in FAOLEX",
      "url": "https://faolex.fao.org/docs/pdf/nep1367.pdf",
      "kind": "Primary legal text reproduced in FAO legal repository",
      "status": "Selected text reviewed; currency pending",
      "checked_on": "2026-11-03",
      "pinpoint": "Sections 2(a), 3–4, 7–8; PDF pp. 1–5",
      "summary": "The English text includes groundwater, vests ownership in Nepal, requires a license subject to listed exemptions, and prohibits harm to others. Section 8 requires economic, technical and environmental material for utilization applications.",
      "verification_needed": "Government-hosted copy timed out; FAOLEX supplies readable legislation, not a current consolidation guarantee. Verify Nepali amendments, commencement notice, prescribed land-confined-water exemption and later special regimes. Land ownership alone does not establish an exemption."
    },
    {
      "id": "NP05",
      "title": "Environment Protection Act 2076 and Regulation 2077 — government index",
      "url": "https://dmgnepal.gov.np/en/resources/acts-and-regulations-3417",
      "kind": "Government legal index",
      "status": "Official index reviewed",
      "checked_on": "2026-11-03",
      "pinpoint": "Index items 10 and 12",
      "summary": "The department’s index lists the Environment Protection Act 2076 and Environment Protection Regulation 2077. The index establishes source availability, not a data-center-specific assessment trigger.",
      "verification_needed": "Retrieve current Act, amended regulations and schedules. Determine BES/IEE/EIA triggers for the actual facility, associated power/water works and location; verify hearing and cumulative-impact requirements."
    },
    {
      "id": "NP06",
      "title": "Privacy Act, 2075 — Nepal Law Commission",
      "url": "https://lawcommission.gov.np/content/12261/the-privacy-act-2075/",
      "kind": "Official legal publication",
      "status": "Official source lead",
      "checked_on": "2026-11-03",
      "pinpoint": "Title-level discovery; provisions not reviewed",
      "summary": "A Law Commission publication identifies the Privacy Act. No substantive privacy, localization, transfer or access rule is verified by this record.",
      "verification_needed": "Review current Nepali text and rules, sector-specific duties, lawful-access powers, cross-border transfers and controller/provider responsibilities. Do not infer blanket localization from the title."
    },
    {
      "id": "NP07",
      "title": "Electronic Transactions Act, 2063 — Nepal Law Commission",
      "url": "https://lawcommission.gov.np/content/13397/",
      "kind": "Official legal publication",
      "status": "Official source lead",
      "checked_on": "2026-11-03",
      "pinpoint": "Act title; section 79 referenced by NP02",
      "summary": "The Law Commission indexes the Electronic Transactions Act. The directive translation cites it as enabling authority.",
      "verification_needed": "Retrieve amended Act, verify section 79 delegation and interplay with newer enactments or pending bills. A bill is not an operative replacement without enactment and commencement checks."
    },
    {
      "id": "NP08",
      "title": "Electricity Act 2049 / Electricity Rules 2050 — Department of Electricity Development",
      "url": "https://doed.gov.np/category/policiesactsrules/?page=2",
      "kind": "Official legal index",
      "status": "Official source lead",
      "checked_on": "2026-11-03",
      "pinpoint": "Electricity Act and Rules index",
      "summary": "The department indexes the Electricity Act and Rules. No data-center tariff or interconnection entitlement is established in this review.",
      "verification_needed": "Review current electricity and regulator legislation, NEA tariff orders, connection rules, large-load contracts and self-generation requirements; confirm which body can impose cost and curtailment conditions."
    },
    {
      "id": "NP09",
      "title": "Local Government Operation Act, 2074 — government publication",
      "url": "https://daokailali.moha.gov.np/en/post/local-government-operation-act-2074",
      "kind": "Official legal publication",
      "status": "Official index reviewed",
      "checked_on": "2026-11-03",
      "pinpoint": "Publication page; operative text not reviewed",
      "summary": "A government publication page identifies the Act. Site-specific municipal and provincial approvals remain unestablished.",
      "verification_needed": "Map constitutional allocation of powers, current Act and relevant municipality’s land-use, building, fire, noise, groundwater and waste rules. Obtain actual permits for a case-study site."
    },
    {
      "id": "NP10",
      "title": "Nepal Electricity Authority — annual reports",
      "url": "https://www.nea.org.np/en/category/annual-reports?page=1",
      "kind": "Official empirical source",
      "status": "Official index reviewed",
      "checked_on": "2026-11-03",
      "pinpoint": "Annual-report index; datasets not extracted",
      "summary": "NEA provides annual reports for electricity-system research. No numerical conclusion about spare capacity, reliability or project load is made here.",
      "verification_needed": "Extract monthly generation/import/export, dry-season supply, peak load, regional network constraints and tariffs from the latest report; document units and reporting period."
    },
    {
      "id": "US01",
      "title": "Minnesota Statutes § 216B.1622 — service to very large customers",
      "url": "https://www.revisor.mn.gov/statutes/cite/216B.1622",
      "kind": "Comparative controlling text",
      "status": "Text reviewed; implementation pending",
      "checked_on": "2026-11-03",
      "pinpoint": "Subdivisions 1–2",
      "summary": "The commission must define very-large-customer classes by December 15, 2026. Tariff/agreement review considers attributable costs, clean-energy benchmarks and protection of other customers against stranded costs.",
      "verification_needed": "Check subdivision 3 exemptions and utility-specific orders before applying the model to a particular Minnesota facility. Nepal transferability requires a separate authority and capacity assessment."
    },
    {
      "id": "US02",
      "title": "Minnesota Statutes § 103G.271, subdivision 5b — water permit conditions",
      "url": "https://www.revisor.mn.gov/statutes/cite/103G.271#stat.103G.271.5b",
      "kind": "Comparative controlling text",
      "status": "Text reviewed",
      "checked_on": "2026-11-03",
      "pinpoint": "Subdivision 5b(a)–(b)",
      "summary": "Covered data-center water permits above the stated 100-million-gallon annual threshold address public welfare, conservation and water-use conflicts. An aquifer test is required when the commissioner finds it necessary for protection.",
      "verification_needed": "Check definitions and full applicability. This threshold belongs to Minnesota; it is not a proposed Nepal threshold or a guarantee of adequate water protection."
    },
    {
      "id": "US03",
      "title": "Oregon HB 3546 (2025), enrolled text",
      "url": "https://olis.oregonlegislature.gov/liz/2025R1/Downloads/MeasureDocument/HB3546",
      "kind": "Comparative legislative text",
      "status": "Text reviewed; implementation check needed",
      "checked_on": "2026-11-03",
      "pinpoint": "Section 3(1)(b)(A)(ii)–(iv), enrolled pp. 1–2",
      "summary": "Covered electricity-service contracts must last at least ten years and provide commission-determined minimum payments tied to projected use.",
      "verification_needed": "Check enacted/codified text, definitions, utility orders, tariff implementation and litigation before treating an individual contract as controlled by this text. Do not transplant a ten-year term without Nepal-specific analysis."
    },
    {
      "id": "US04",
      "title": "Fairfax County adopted data-center zoning amendment",
      "url": "https://www.fairfaxcounty.gov/planning-development/sites/planning-development/files/Assets/Documents/zoning%20ordinance/adopted%20amendments/ZO_112_1-2024-9.pdf",
      "kind": "Comparative adopted ordinance",
      "status": "Adopted text reviewed; current codification pending",
      "checked_on": "2026-11-03",
      "pinpoint": "§ 4102.6.A(1), (6) and transition provisions; PDF pp. 3–5",
      "summary": "The adopted amendment addresses operating-equipment enclosure and noise studies before site-plan approval and occupancy, with exceptions and transition provisions.",
      "verification_needed": "Check current clean codification and later amendments; distinguish zoning noise studies from the separate noise ordinance. These are county-specific rules."
    },
    {
      "id": "EU01",
      "title": "European Commission — sustainability reporting scheme",
      "url": "https://energy.ec.europa.eu/news/commission-adopts-eu-wide-scheme-rating-sustainability-data-centres-2024-03-15_en",
      "kind": "Official explanatory summary",
      "status": "Official summary reviewed",
      "checked_on": "2026-11-03",
      "pinpoint": "March 15, 2024 announcement",
      "summary": "The Commission describes recurring data-center sustainability reporting and indicators concerning energy, water, renewable energy and waste heat.",
      "verification_needed": "EUR-Lex retrieval met a verification screen. Review Regulation (EU) 2024/1364 and Directive (EU) 2023/1791 for current scope, thresholds, confidentiality and amendments; this summary is not controlling text."
    },
    {
      "id": "NP11",
      "title": "Data Center and Cloud Service Directive, 2081 — Nepali government-hosted copy",
      "url": "https://giwmscdnone.gov.np/media/pdf_upload/डाटा%20सेन्टर%20निर्देशिका_shicxzc.pdf",
      "kind": "Government-hosted Nepali legal text",
      "status": "Selected Nepali clauses visually checked",
      "checked_on": "2026-11-03",
      "pinpoint": "Clauses 3(1), 3(13), 4 and 6(3); signed scan PDF pp. 2, 4–5; approval line p. 1",
      "summary": "Clause 3 requires listing before service and separate listings for the two services. Clause 4 requires details updated by Poush-end annually. Clause 6(3) sets Tier III or higher for providers storing government data.",
      "verification_needed": "PDF downloaded; selected clauses checked against page images because indexed OCR garbles numbering and dates. Approval line appears to read 2081/10/15; obtain Nepali-law/date reconciliation before using a transition deadline. Annex, amendments, current office and implementation remain unchecked."
    },
    {
      "id": "NP12",
      "title": "Water Resources Rules, 2050 (1993) — Law Commission English text in FAOLEX",
      "url": "https://faolex.fao.org/docs/pdf/nep100346.pdf",
      "kind": "Primary legal text reproduced in FAO legal repository",
      "status": "Selected text reviewed; currency pending",
      "checked_on": "2026-11-03",
      "pinpoint": "Rules 8, 17–20 and 22; PDF pp. 3, 6–9",
      "summary": "The reproduced rules assign licensing to a District Water Resources Committee. Rule 17 requests project and environmental information; rule 19 provides public notice, 35 days for reasoned adverse-impact reactions, and license conditions addressing reactions. Rule 22 confines use to the licensed works, place and area.",
      "verification_needed": "Verify current Nepali rules and post-federal institutional succession. This older structure does not settle today’s competent office, a special Valley route, or a project’s separate environmental-assessment obligations."
    },
    {
      "id": "NP13",
      "title": "Kathmandu Valley Water Supply Management Board — action plan",
      "url": "https://kvwsmb.org.np/page/action_plan",
      "kind": "Official administrative practice / plan",
      "status": "Official plan text reviewed",
      "checked_on": "2026-11-03",
      "pinpoint": "Short-term groundwater licensing items; mid-term legal/policy clarity item",
      "summary": "The Board describes licensing groundwater users, including shallow commercial users, and monitoring licensed wells. It also seeks legal and policy clarity under the federal structure.",
      "verification_needed": "Undated planning evidence only. Its shallow-commercial licensing aspiration does not settle current entitlement: assess NP14 rules 2, 10, 15–16 and site restrictions. Confirm the notified Board boundary and current intake requirements."
    },
    {
      "id": "NP14",
      "title": "Kathmandu Valley Water Supply Management Board Rules, 2082 — Board-hosted signed scan",
      "url": "https://www.kvwsmb.org.np/public/uploads/board_act_%26_rules/1763624992-52256.pdf",
      "kind": "Official Board-hosted Nepali rules",
      "status": "Selected operative rules visually checked",
      "checked_on": "2026-11-03",
      "pinpoint": "Rules 10–11, 13–16, 39–40; Schedules 3–4; PDF pp. 4–7, 12, 15–16",
      "summary": "Rule 10 provides Board-issued deep-boring permits; Schedule 3 addresses the Executive Director. Rule 11 separately licenses drilling providers; rule 13 covers tanker/jar/bottling services. Rule 14 sets three-year terms and renewal applications 30 days before expiry. Rule 40 repeals the 2064 rules and saves actions under them.",
      "verification_needed": "Signed 22-page scan retrieved from the Board’s rules index. Confirm later amendments, current fees and notices, site restrictions and delegated signatory. Rule 16 permits location-specific restrictions; rule 15 exemptions require exact use and well classification. No guaranteed 30-day approval or universal extraction allowance is established."
    },
    {
      "id": "NP15",
      "title": "Provider-listing notice — Information Technology and Digital Governance Office",
      "url": "https://doit.gov.np/content/12083/notice-issued-to-be-listed-to-data/",
      "kind": "Official implementation notice",
      "status": "Official indexed notice text reviewed",
      "checked_on": "2026-11-03",
      "pinpoint": "Notice page dated 20 Mangsir 2082; separate application-form links",
      "summary": "The official notice links separate listing application formats for data-center and cloud providers and references the 2081 directive.",
      "verification_needed": "Read the notice attachment and both current forms. A webpage repost date does not establish a new legal deadline, extension, fee or continuing validity of the original transition period."
    },
    {
      "id": "NP16",
      "title": "Water Supply Management Board Act, 2063 — Board-hosted Nepali text",
      "url": "https://kvwsmb.org.np/public/uploads/board_act_%26_rules/rule-4.pdf",
      "kind": "Official Board-hosted Nepali Act",
      "status": "Selected authority provisions visually checked",
      "checked_on": "2026-11-03",
      "pinpoint": "Sections 5, 7(8)(c), 35–36; PDF pp. 4, 6, 14",
      "summary": "Section 7(8)(c) authorizes the Valley Board to regulate, restrict or prohibit groundwater extraction/use and issue prescribed permits within its territory, except where prevailing law provides otherwise. Section 5 ties boundaries to Gazette notification; sections 35–36 provide rule/directive powers.",
      "verification_needed": "This Board copy lists an older amendment; it is not certified current consolidation. Obtain subsequent amendments and the operative geographic notifications. Institutional authority does not establish that a specific parcel or proposed extraction is approved."
    },
    {
      "id": "NP17",
      "title": "Groundwater extraction/use permit directive, 2071 — older Board-hosted text",
      "url": "https://kvwsmb.org.np/public/uploads/board_act_%26_rules/rule-1.pdf",
      "kind": "Official Board-hosted historical procedural text",
      "status": "Older text reviewed; present status unresolved",
      "checked_on": "2026-11-03",
      "pinpoint": "Cover approval note; clauses 6–8; PDF pp. 1, 4–5",
      "summary": "The older directive requests local recommendations, technical materials and local hearing/discussion reports for industrial, commercial and public uses. It sets a staged construction and abstraction process.",
      "verification_needed": "The 2071 cover and older 2064-rule references differ from the Board’s later report referring to a 2073 directive. Retrieve that version and reconcile with 2082 rule 40. Do not present this older checklist, fees or hearing procedure as confirmed current requirements."
    },
    {
      "id": "NP18",
      "title": "KVWSMB — published institutional roles",
      "url": "https://kvwsmb.org.np/page/about",
      "kind": "Official institutional explanation",
      "status": "Official role statement reviewed",
      "checked_on": "2026-11-03",
      "pinpoint": "Roles & Responsibilities; institutional setup; working office",
      "summary": "The Board identifies groundwater regulation and license issuance as its role. It describes KUKL as operating the transferred system under lease/license and places the Board office in Sainbu, Bhaisepati, Lalitpur.",
      "verification_needed": "This supports the institutional distinction, not a permit delegation to KUKL or proof of today’s named signatory. Read rule 39 delegation and obtain the current Board application instructions; no contact has been made."
    }
  ],
  "rows": [
    {
      "id": "N01",
      "topic": "Entry, registration & service scope",
      "nepal_baseline": "Reviewed Nepali clauses require pre-service listing, separate listings for data-center and cloud services, and annual Poush-end updates (NP11). A separate official notice links application formats (NP15).",
      "evidence": "Partial baseline",
      "source_ids": [
        "NP11",
        "NP15",
        "NP01",
        "NP02",
        "NP07"
      ],
      "verification_question": "Confirm the signed approval date, current office, forms, covered actors and amendments. Reconcile existing-operator transition and certification provisions before assigning a deadline.",
      "comparators": [],
      "policy_option": "Build an approvals map distinguishing facility owner, colocation operator, cloud provider and tenant.",
      "transferability": "Listing is one approval layer. It does not establish water, environmental or municipal clearance. Clause 6(3)’s government-data Tier III requirement is not a blanket tier rule for every facility.",
      "priority": "High"
    },
    {
      "id": "N02",
      "topic": "Water allocation & groundwater",
      "nepal_baseline": "KVWSMB is the text-supported groundwater permit authority for its Valley jurisdiction (NP16). Under the 2082 rules, deep-boring users apply to the Board; Schedule 3 addresses its Executive Director. Drilling providers and tanker/jar/bottling services have separate permits (NP14). General national priorities remain relevant background (NP04).",
      "evidence": "Partial baseline",
      "source_ids": [
        "NP14",
        "NP16",
        "NP18",
        "NP04",
        "NP12",
        "NP17",
        "NP13"
      ],
      "verification_question": "Confirm parcel jurisdiction, current restrictions/fees, use and well category. The domestic/religious-use exemptions do not establish an industrial-cooling exemption. Identify the authorized signatory and reconcile later directives. For purchased water, verify supplier and source permits.",
      "comparators": [
        "US02"
      ],
      "policy_option": "Evaluate source-specific water budgets, drought stages, metering, aquifer testing and enforceable restrictions on consumptive cooling.",
      "transferability": "For a project borewell, start with KVWSMB rather than treating KUKL’s supply contract or a municipal recommendation as abstraction permission. This is an authority map, not clearance. The older national committee process must not be substituted automatically for the Valley route.",
      "priority": "High"
    },
    {
      "id": "N03",
      "topic": "Electricity, grid upgrades & exit risk",
      "nepal_baseline": "Electricity-law and NEA sources are identified; no current data-center-specific tariff, guaranteed supply entitlement or cost-allocation rule has been verified.",
      "evidence": "Open baseline",
      "source_ids": [
        "NP08",
        "NP10"
      ],
      "verification_question": "Who pays for connection and upstream upgrades, unused reserved capacity, curtailment and early exit? What is available in the dry season?",
      "comparators": [
        "US01",
        "US03"
      ],
      "policy_option": "Assess study deposits, collateral, staged load commitments, minimum bills and exit-cost guarantees.",
      "transferability": "Test utility/regulator authority, foreign-exchange risks, enforceability and demand uncertainty before recommending any contract term.",
      "priority": "High"
    },
    {
      "id": "N04",
      "topic": "Environmental review & cumulative effects",
      "nepal_baseline": "A government index lists the environmental Act and Regulation. The exact assessment category and approving body for a data center and associated works remain unverified.",
      "evidence": "Open baseline",
      "source_ids": [
        "NP05"
      ],
      "verification_question": "Which current schedule entries trigger review for buildings, water works, generators, substations or transmission lines? Are cumulative projects and expansions assessed?",
      "comparators": [
        "US04"
      ],
      "policy_option": "Consider coordinated review of the facility and associated infrastructure, alternatives and cumulative impacts.",
      "transferability": "Do not assert every data center requires a full EIA. Establish the actual statutory trigger and institutional jurisdiction.",
      "priority": "High"
    },
    {
      "id": "N05",
      "topic": "Siting, noise, air & local approvals",
      "nepal_baseline": "The local-government Act is identified. Applicable municipality-specific siting, noise, fire and emissions standards are not yet established.",
      "evidence": "Open baseline",
      "source_ids": [
        "NP09",
        "NP05"
      ],
      "verification_question": "Which municipality/province has approval and enforcement powers? Which rules cover cooling equipment, diesel generators, fuel storage and sensitive neighbors?",
      "comparators": [
        "US04"
      ],
      "policy_option": "Evaluate preconstruction and operating noise studies, setbacks, equipment mitigation and public permit conditions.",
      "transferability": "Account for low-frequency sound and site conditions, but verify the measurement standard and legal power before proposing numerical limits.",
      "priority": "High"
    },
    {
      "id": "N06",
      "topic": "Foreign investment & contractual structure",
      "nepal_baseline": "Selected provisions of a government-hosted 2019 English FITTA text were reviewed. Current amendment, notification and sector-classification checks remain open.",
      "evidence": "Partial baseline",
      "source_ids": [
        "NP03"
      ],
      "verification_question": "What current approvals and restrictions apply to ownership, technology transfer, financing and repatriation? Does a PPP or government agreement alter the approval path?",
      "comparators": [],
      "policy_option": "Prepare separate approval maps for private FDI, PPP and government arrangements; disclose ownership and contingent public liabilities.",
      "transferability": "Do not assume an investment agreement overrides general environmental, water, privacy or municipal law. Obtain current Nepali texts and project documents.",
      "priority": "High"
    },
    {
      "id": "N07",
      "topic": "Privacy, cybersecurity & cross-border data",
      "nepal_baseline": "Official Privacy Act and Electronic Transactions Act sources, plus the directive, are identified. Their operative obligations and interactions are not yet fully reviewed.",
      "evidence": "Open baseline",
      "source_ids": [
        "NP01",
        "NP06",
        "NP07"
      ],
      "verification_question": "Who controls data, who may access it, what sector-specific hosting or transfer duties apply, and who handles incidents and service continuity?",
      "comparators": [],
      "policy_option": "Map data categories and responsible entities; evaluate audit, access controls, incident reporting, portability and continuity obligations.",
      "transferability": "A physical facility’s location does not by itself settle jurisdiction, ownership of data, or lawful government access. Do not assert a general localization mandate.",
      "priority": "High"
    },
    {
      "id": "N08",
      "topic": "Public finance, jobs & local benefits",
      "nepal_baseline": "The investment text provides an entry point. Current tax incentives, budget measures and any data-center-specific benefit conditions have not been verified.",
      "evidence": "Open baseline",
      "source_ids": [
        "NP03"
      ],
      "verification_question": "What exemptions, subsidies, public works or guarantees apply, and what independently supported jobs and tax benefits remain after those costs?",
      "comparators": [],
      "policy_option": "Test incentives against measurable employment, procurement, tax and infrastructure outcomes; assess disclosure and recapture options.",
      "transferability": "Separate temporary construction jobs from permanent operations. Compare net public benefit with feasible alternatives; no job multiplier is assumed.",
      "priority": "Medium"
    },
    {
      "id": "N09",
      "topic": "Transparency & public participation",
      "nepal_baseline": "The general Water Resources Rules provide a 35-day adverse-impact response route (NP12). The older Valley directive describes local hearings (NP17), but its current status is unresolved after replacement of the 2064 rules. Do not assume the same procedure applies to every Valley permit.",
      "evidence": "Partial baseline",
      "source_ids": [
        "NP12",
        "NP14",
        "NP17",
        "NP05",
        "NP09"
      ],
      "verification_question": "Obtain current Valley hearing/notice instructions and the later groundwater directive; establish how these interact with environmental review and local consultation. Preserve the distinction between the national water route and special Valley permits.",
      "comparators": [
        "EU01",
        "US04"
      ],
      "policy_option": "Assess public project registers and consistent energy/water reporting, with narrowly justified security and confidentiality limits.",
      "transferability": "EU reporting is a comparison lead. Identify Nepal’s existing disclosure duties and agency resources before adding reporting layers.",
      "priority": "High"
    },
    {
      "id": "N10",
      "topic": "Enforcement, closure & ownership changes",
      "nepal_baseline": "No data-center-specific decommissioning security, successor-liability or long-term restoration requirement has been established in this baseline. That is a research gap, not evidence of absence.",
      "evidence": "Open baseline",
      "source_ids": [
        "NP01",
        "NP03",
        "NP05"
      ],
      "verification_question": "Which general laws and permits address closure, equipment/waste disposal, groundwater harm, abandoned grid assets and transfer of ownership?",
      "comparators": [
        "US01",
        "US03"
      ],
      "policy_option": "Evaluate closure plans, financial security, transferable permit duties and asset-specific exit obligations.",
      "transferability": "Distinguish utility stranded costs from land restoration and waste liability. Each may require a different authority, beneficiary and enforcement route.",
      "priority": "High"
    }
  ],
  "method": [
    "Evidence status describes what was actually examined, not whether a law is valid or effective.",
    "Text reviewed does not mean current consolidated law verified. Indexed excerpts and official indexes remain separate from full-text review.",
    "Valley update: Board authority and the 2082 deep-boring permit route are supported by reviewed Nepali text. Older 2064 rules were repealed; current directives, amendments and project applicability remain open.",
    "A missing record means this research is incomplete. It does not establish a legal vacuum.",
    "Comparison mechanisms are jurisdiction-specific. Proposed Nepal options are analytical questions, not statements of Nepal law.",
    "No project pipeline, jobs forecast, water-use estimate or electricity-capacity claim has been verified in this edition."
  ],
  "next_steps": [
    {
      "priority": "1",
      "task": "Reconcile the signed Nepali directive with NP11 extraction, annex and implementation forms; confirm current administering office and amendments.",
      "owner": "Nepali-law reviewer to be assigned",
      "completion": "Verified approval/commencement date, clause-level checklist and dated amendment search."
    },
    {
      "priority": "2",
      "task": "Choose one real or clearly hypothetical project with location, owner, capacity, cooling source and investment structure.",
      "owner": "Research team",
      "completion": "Project facts sheet separating approvals, announcements and operating facts."
    },
    {
      "priority": "3",
      "task": "Apply the confirmed KVWSMB route to a specified parcel; obtain boundaries, current fees/restrictions, delegated signatory and later groundwater directives.",
      "owner": "Nepali-law reviewer + water specialist",
      "completion": "Board jurisdiction and current checklist confirmed for the well/use; drilling and supplier permits distinguished; later amendments and notices reconciled."
    },
    {
      "priority": "4",
      "task": "Extract current environmental schedules and large-load electricity terms; verify dry-season and network constraints.",
      "owner": "Research team + technical reviewer",
      "completion": "Screening memo, tariff/order citations and dated NEA data."
    },
    {
      "priority": "5",
      "task": "Compare only mechanisms responsive to verified Nepal gaps; record costs, enforcement capacity and legal authority.",
      "owner": "Research team",
      "completion": "Options memo distinguishing existing powers, rulemaking and legislation."
    }
  ]
}